Business project governance for a stalled enterprise systems rollout
A client story in business project governance: A global pharmaceutical client’s stalled enterprise-systems rollout, 18 months behind schedule and 40% over budget, recovered to on-schedule delivery within 9 months through disciplined program governance, workstream redesign, and interim program leadership.
Pharmaceutical – Program management

The opportunity
The opportunity
A top-20 global pharmaceutical company had launched an enterprise-systems program to consolidate manufacturing execution systems (MES) across 14 production sites in North America, Europe, and Asia. The program was sponsored by the Chief Manufacturing Officer, with a 36-month schedule and a $180M budget. Eighteen months into execution, the program had slipped more than 12 months against schedule, was trending toward a 40% budget overrun, and three pilot sites had rolled back to legacy systems.
The CEO commissioned an independent review. The review identified that the program’s technical scope was sound, the MES platform and integration architecture were appropriate, but governance, workstream coordination, and operating-model design were fundamentally broken. WGA Consulting was engaged to rebuild program governance and restore the program to on-schedule delivery. Steering committee at wrong altitude.
The steering committee had grown to 22 members and had become a status-reporting body rather than a decision-making forum. Critical decisions were deferred for weeks or kicked back to individual site leads. Workstream boundaries unclear. Nine workstreams existed on paper; in practice, scope overlap and gaps were creating re-work and blame-shifting between workstreams. Business-process redesign not coordinated with technology. The technology team was configuring the MES to preserve existing site-specific processes rather than deploying a harmonized target state.
No realized-benefits tracking. The $180M business case had never been decomposed into site-level and quarter-level benefit commitments. Finance had no way to validate whether the program was delivering expected value. Program leadership turnover. The program had been through three program directors in 18 months. No one held institutional memory of commitments, decisions, or dependency management.
Change management underfunded.
Site-level adoption work had been deferred to after go-live, which was the root cause of the three pilot-site rollbacks.
The solution
How the business project governance work ran
WGA deployed a team of five senior consultants within three weeks, led by a former Big Pharma CIO as interim Program Director. The approach had three phases running partially in parallel. Phase 1 (weeks 1-4): Diagnostic and governance reset.
We conducted 25 stakeholder interviews, reviewed all steering materials from the prior 18 months, assessed the MES configuration against target-state business processes, and delivered a written governance-reset recommendation to the CEO and steering sponsor. The steering committee was reduced from 22 to 9 voting members with defined decision rights. Monthly steering cadence was replaced with bi-weekly working steering meetings and quarterly strategic steering. Phase 2 (weeks 3-16): Workstream redesign and business-case rebuild.
Nine unstructured workstreams were consolidated into five clearly-scoped workstreams, each with a written charter and named accountable leader. The business case was decomposed into site-level and quarter-level benefit commitments, signed off by site general managers and validated by corporate finance. Every workstream now had weekly metrics tied directly to business-case realization. Phase 3 (weeks 8-36): Execution recovery.
The interim Program Director led weekly program reviews with the five workstream leads, monthly site readiness reviews, and the bi-weekly steering cadence. Three additional sites went live successfully during this phase; the full 14-site rollout completed on the revised schedule with no additional rollbacks. Program governance redesign: steering committee, workstream structure, decision rights, and escalation protocols Interim Program Director for 9 months (senior consultant with prior CIO experience)
Business case rebuild with site-level and quarter-level benefit commitments signed off by site GMs and corporate finance Target-state business-process design with harmonized MES configuration strategy Site-readiness methodology used for the remaining 11 sites: Change-management and site-adoption program integrated into deployment sequence Weekly program metrics and steering dashboard with direct tie to business-case realization
Knowledge transfer to internal program director who took over post-engagement
The impact
The impact
On-Schedule Delivery: Remaining 11 sites deployed on the revised schedule: zero additional rollbacks after the governance reset. Budget Recovery: Total program cost closed at $214M against original $180M budget: a 19% overrun versus the 40% trajectory prior to WGA engagement. $47M of forecast overrun avoided.
Benefit Realization: $52M Year-1 run-rate benefits realized (versus $0 prior to governance reset). Three-year cumulative benefits tracked at 94% of original business case.
Organizational Capability: Internal program director, five workstream leads, and PMO staff retained and strengthened: client self-sufficient in program governance within 9 months.
The technical architecture was not the problem. When enterprise-systems programs fail, governance, business-case discipline, and business-process integration are almost always the underlying causes. Rebuilding those, rather than replacing the technology, is the right recovery path in the majority of cases.
Interim program leadership matters. When a program has lost three program directors in 18 months, internal recruiting won’t fix the problem. Senior interim leadership with operator-level judgment, deployed fast, is often the difference between recovery and program failure.
Steering committee design is underrated. Most enterprise programs have a steering committee that grows over time, dilutes decision rights, and becomes a status-reporting venue. A right-sized steering body, 7-to-9 members with explicit decision rights, is one of the highest-apply interventions available to any program in trouble.